Please Note: This table is intended as a brief reference only,Consortium members should consult the detailed schedule within the members’ area of this web site to identify detailed steps and task responsibilities.
StartDate |
Major Activity |
Extent |
Status |
|---|---|---|---|
Tue 19/04/05 |
Test Server |
|
|
Tue 19/04/05 |
Apply MetaLib Service Packs |
7 days |
Completed |
Wed 27/04/05 |
OS Upgrade |
5 days |
Completed |
Tue 3/05/05 |
SFX Upgrade |
32 days |
Completed |
Tue 3/05/05 |
Members redirect SFX links from suppliers to SFX production url |
10 days |
Completed |
Thu 2/06/05 |
OS Upgrade SFX development server |
7.7 days |
Completed |
Mon 8/08/05 |
SFX 3 upgrade development server |
5 days |
|
Mon 13/06/05 |
OS Upgrade SFX production server |
8 days |
|
Mon 8/08/05 |
SFX 3 upgrade production server |
5 days |
|
Fri 29/04/05 |
MetaLib Service Packs applied to MetaLib Servers |
7.5 days |
Completed |
Mon 23/06/05 |
OS Upgrade MetaLib development server |
6.7 days |
Completed |
Thu 30/06/05 |
OS Upgrade MetaLib production server |
8.2 days |
Completed |
Mon 1/08/05 |
Test Server MetaLib 3.13 Upgrade and AARLIN setup |
10 days |
|
Mon 22/08/05 |
Members access MetaLib 3.13 on Test Server for inspection |
20 days |
|
Mon 19/09/05 |
MetaLib 3.13 Upgrade development server |
7 days |
|
Mon 26/09/05 |
MetaLib 3.13 Upgrade production server |
7 days |
|